A planning timeline for event connectivity

Connectivity problems on show day are usually decisions that were made too late. This timeline sets out what belongs at each stage, so the slow parts start early and the details settle in the right order.

Last reviewed November 2026 · 6 min read

On this page

Key takeaways

  • Start connectivity conversations when you shortlist venues, not after you sign. Venue rules can decide your options.
  • New internet connections can take weeks to deliver. Find out lead times early and work backwards.
  • Lock the design a few weeks out, stage and test the configuration before you travel, and test again on site before doors open.
  • Every event should end with a report that makes the next one easier to plan.

Why timing matters more than budget

Many connectivity failures trace back to a single late discovery: the venue only allows its in-house provider, the fibre order needed six weeks and was placed with two, or nobody told the network team about a live stream until the day before. Money cannot always buy back time. A sensible timeline makes sure the slow, irreversible decisions are made first.

The stages below are typical for a mid-sized or large event. Smaller events can compress them, and very large or remote events often need more time, especially where new connections have to be built. Ask each supplier for their real lead times and plan from those.

At a glance

StageTypical timingFocus
Venue shortlistBefore contractsVenue rules, available internet sources, exclusivity and fees
Brief and proposalsEarly planningWritten requirements, supplier conversations, site survey
Order long-lead itemsAs soon as the design is agreedInternet circuits, permits, special equipment
Design lockA few weeks outAccess point plan, network names, security, IP plan, power
Pre-build preparationFinal weeksConfiguration staged and tested, spares, contacts, run sheet
Build and testBuild daysInstall, verify every system, failover test, walk test
Show daysLiveMonitoring, support desk, change control
DebriefWithin days afterReport, lessons learned, data for next time

Stage 1: venue shortlist

Before signing a venue contract, find out how connectivity works there. Some venues have excellent permanent infrastructure and an in-house team. Others have little more than a broadband line in the office. Many fall somewhere in between, with rules about who may install equipment and what that costs.

Ask whether outside providers are permitted, whether there are fees for using the venue’s network or cabling, which internet sources already reach the building, and whether there are restrictions on mounting equipment or running cables. The full list of questions is in assessing a venue’s connectivity. The answers can change your budget significantly, so they are worth having before you commit.

Stage 2: brief and proposals

Once the venue is confirmed, write down what the network must do. A clear brief lets suppliers propose like-for-like solutions and stops important requirements, such as a second live stream or a cashless bar, being remembered too late. Use the connectivity brief template as a starting point.

This is also the right moment for a site survey. Good suppliers will want to see the venue, measure the radio environment, check cable routes and test mobile signal before proposing a design. What a site survey covers explains what to expect.

Stage 3: order long-lead items

As soon as a design is agreed in principle, order anything that takes time to arrive:

  • New internet circuits. A dedicated fibre connection to a venue that does not already have one can take weeks, sometimes longer if construction or permissions are involved.
  • Permits and permissions. Outdoor venues may need approvals for cabling, masts or trenching.
  • Special equipment. Outdoor-rated access points, long fibre runs, or large quantities of a particular switch may need to be sourced.
  • Venue services. Rigging time, ceiling access, power distribution and patching often need booking.

If a long-lead item cannot be delivered in time, it is far better to know now and plan an alternative, such as bonded cellular, than to discover it during the build.

Stage 4: design lock

A few weeks before the event, the design should be fixed so everyone can work from the same plan. By this point you should have agreed:

  • Floor plans showing access point locations and cable routes
  • The list of network names, who uses each one and how people log in
  • Bandwidth allocation and traffic priorities, including streams
  • An IP addressing plan sized for the expected number of devices
  • Power requirements, including UPS for core equipment
  • Wired connection points for stages, registration, payments and press
  • Exhibitor ordering deadlines and the rules they must follow
  • Security settings, monitoring and support arrangements

Changes after this point are still possible, but each one should be deliberate and recorded.

Stage 5: pre-build preparation

In the final weeks, the network team prepares so the build is assembly rather than invention. Equipment is configured and powered up in a workshop, tested together and labelled. Spare access points, switches and cables are packed. Contact lists and escalation paths are confirmed, including the venue’s engineer and every production supplier who will need a connection.

Agree the build schedule with other trades. Network cabling often has to go in before carpets and staging, and access points may need to be rigged while lifts are available.

Stage 6: build and test

On site, install, power up and verify everything, then test it the way it will be used. That means testing each network name on several device types, checking that critical devices work on their own connections, running a test stream to the real platform and deliberately disconnecting the main internet source to prove failover works. Pre-show network testing has a complete checklist.

Leave time to fix what testing reveals. A test that finishes ten minutes before doors open is a test you cannot act on.

Stage 7: show days

During the event, someone should be watching the network continuously, with a clear way for staff and producers to report problems. Avoid configuration changes during sessions unless they fix a live problem. What to monitor while the event is live covers the dashboard and the people side.

Stage 8: debrief

Within a few days, ask for a report: peak devices, peak bandwidth in each direction, incidents and how they were resolved, and recommendations. Combine it with feedback from attendees, exhibitors and production. This turns one event’s experience into evidence for the next, and gives you real numbers instead of guesses next time you use the bandwidth calculator.

Where to go next

The most useful single document in this timeline is the brief, so a good next step is the connectivity brief template, which lists every section a supplier needs to see.

If your venue is not yet confirmed, assessing a venue’s connectivity gives you the questions to ask during site visits.